"SKILITSIO" GENERAL HOSPITAL IN CHIOS
Project's Description

- Addition of a new wing and auxiliary reinforced concrete buildings at the existing building of Chios General Hospital.
Strengthening of existing masonry buildings 1 and 4 using sprayed concrete.
- Special foundation on piles for the maintenance - set off of antiquities found under the foundation level.

Project's Details
  • Client: DEPANOM S.A. / AKTOR S.A.
  • Design Stages: Scheme and Detailed Design
  • Budget (Structural): 1,000,000 €
  • Design Period: 09/06/2005 – 30/03/2006
  • Project State: Completed
  • Architectural Design: BETAPLAN A.E.M.
  • MEP Design: AKTER Ltd